Chinese New Year 2027: A Replacement Parts Ordering Timeline for Buyers

Writer: Cici Wu
Cici Wu
Nov 3
3 min read

Chinese New Year falls on February 6, 2027. For anyone sourcing vacuum cleaner and robot vacuum replacement parts from China, the real deadline comes much earlier than that.


Here is our factory schedule for the 2027 holiday, and the timeline we recommend to buyers who want stock on the shelf in Q1.


The period before the Spring Festival holiday is always peak shipping season.
The period before the Spring Festival holiday is always peak shipping season.

Our 2027 holiday schedule


  • After January 10, 2027: Order capacity starts to tighten

  • Around January 25, 2027: Factory production STOPS

  • February 6, 2027: Chinese New Year's Day

  • Around February 15, 2027: Factory reopens


Chinese New Year is the one holiday when almost every worker goes home, often to another province, for an extended break. Production lines do not run on reduced staff during this period. They stop.


Our order cut-off is normally 10 to 15 days before production stops. In practice, that means orders received after January 10 may not be scheduled before the holiday. If you need goods produced before the break, plan to place your order early.


Custom products need the most lead time


Standard, regular items are the easiest to schedule before the holiday. Custom products are not.


If your order involves anything outside our regular range, such as a new mold, a modified specification, a private label package, custom printed bags or a new product combination, each step takes time:


  • Confirming drawings or specifications

  • Making and approving samples

  • Sourcing special materials or packaging

  • Printing and checking labels and cartons


If any one of these steps is still open in early January, the order will very likely slip to after the holiday. Please confirm all details of custom products as early as possible. For private label projects, our guide on custom product labels for robot vacuum accessories explains what information we need from you.


Our recommended timeline


  • November to early December 2026: confirm custom items

Finalize specifications, approve samples and lock packaging and label files for any custom or new products. This leaves enough room for revisions.

  • December 2026: place orders for Q1 stock

Send purchase orders for both standard and confirmed custom items. Review your Q1 sales plan and add a buffer for fast-moving consumables such as filters, side brushes, main brushes, mop pads and dust bags.

  • By January 10, 2027: final orders

Treat January 10 as your practical last day to place orders you need produced before the break. Orders after this date will be confirmed case by case.

  • January 2027: book shipping early

Freight space is usually tight in the weeks before Chinese New Year, as many factories try to ship at the same time. Discuss shipping dates with us early and book space ahead.

  • After February 15, 2027: production restarts

Orders placed during the holiday will be scheduled in sequence after we reopen. Allow some time for production to return to full speed.


A simple planning check


Before the end of the year, we suggest buyers ask three questions:


  1. How many weeks of stock do I need to cover the period from late January to March?

  2. Which of my items are custom and still not fully confirmed?

  3. Have I agreed on a shipping date, not only a production date?


If the answer to the second question is anything other than "none," that is the item to work on first.


Plan your pre-holiday order with us


If you are planning Q1 stock of vacuum or robot vacuum replacement parts, contact the LongboTEK team now. We will help you check your list, confirm which items can still be produced before the break and arrange a realistic shipping schedule.